SAFe Scrum Master (SSM) — Question 22
Team A has decided to use the IP Iteration to continue the finalizing Feature delivery work they have been working on for the past two Iterations. What is one effect Team A might experience by continuing to stay heads-down rather than using the IP Iteration as intended?
Answer options
- A. Individual team members could lose an opportunity to refresh their motivation
- B. Individual team members could lose an opportunity to keep their technical skills current
- C. Individual team members could lose an opportunity to consider their team work more holistically
- D. Individual team members could lose an opportunity to learn from one another
Correct answer: A
Explanation
The correct answer is A because staying heads-down on delivery can lead to burnout and reduced motivation among team members. Options B, C, and D, while valid concerns, do not directly address the immediate impact on motivation that is crucial for ongoing productivity and engagement.