SAFe Scrum Master (SSM) — Question 21
According to SAFe, which of the following metrics are reported at the Inspect and Adapt event?
Answer options
- A. Cumulative value measure
- B. ART predictability measure
- C. ART cycle velocity
- D. Cumulative value rate
Correct answer: B
Explanation
The correct answer is B, as the ART predictability measure is specifically used to assess how well the Agile Release Train can predict its planned outcomes during the Inspect and Adapt event. The other options, while related to value and performance, do not pertain directly to the metrics reported at this specific event.