SAFe Scrum Master (SSM) — Question 19
Which of the following events aligns teams on a train?
Answer options
- A. PI Planning
- B. Coach Sync
- C. Architect Sync
- D. Iteration Planning
Correct answer: A
Explanation
PI Planning is a key event in the SAFe framework that brings all teams on a train together to align on objectives and plans for the upcoming Program Increment. The other options, while important, do not serve the same purpose of aligning all teams; Coach Sync focuses on coaching practices, Architect Sync on architectural considerations, and Iteration Planning on specific team iterations.