SAFe Scrum Master (SSM) — Question 18
During which of the following Agile Team events do team members estimate relative story sizes?
Answer options
- A. Iteration Retrospective
- B. Backlog Refinement
- C. Iteration Review
- D. Iteration Planning
Correct answer: B
Explanation
The correct answer is B, Backlog Refinement, as this event is specifically designed for the team to discuss and estimate the size of user stories in preparation for future iterations. The other options, such as Iteration Retrospective and Iteration Review, focus on reflecting on past work and reviewing completed work, rather than estimating story sizes.