SAFe Scrum Master (SSM) — Question 13
What is one anti-pattern of the Inspect and Adapt?
Answer options
- A. Not enough team members attend the PI System demo
- B. No actionable improvement Features are created
- C. Too many ideas enter the problem-solving workshop
- D. Only one problem is identified by each team in the retrospective
Correct answer: A
Explanation
The correct answer, A, highlights the issue of low attendance at the PI System demo, which can hinder effective feedback and learning. Options B and D point to the lack of actionable improvements and the limitation of identified problems, respectively, while C describes an overload of ideas, but none of these directly address the crucial participation aspect of the demo.