SAFe Scrum Master (SSM) — Question 12
What is one recommended practice for Scrum Masters/Team Coaches when coaching teams on presenting a draft plan at PI Planning?
Answer options
- A. Identify as many risks and dependencies as possible for the management review
- B. Align on how the team will answer questions about their proposed objectives
- C. Secure support from other teams on how work will be shared and completed
- D. Ensure the team has Stories written for the first two Iterations of the increment
Correct answer: B
Explanation
The correct answer, B, emphasizes the importance of preparing the team to effectively communicate their goals during PI Planning. Options A and C focus on risk management and collaboration with other teams, which are important but secondary to ensuring clarity in objectives. Option D, while relevant to planning, does not directly address the presentation aspect of the draft plan.