SAP Certified Application Associate – SAP S/4HANA Sales (2022) — Question 14

In which type of outline agreement would you see details of confirmed material quantities and delivery dates?

Answer options

Correct answer: C

Explanation

The correct answer is C, Scheduling agreement, as it specifically includes confirmed material quantities and delivery dates. The other options, like the General value contract and Material-related value contract, do not focus on confirmed quantities and dates, while a Quantity contract is more about the total quantity rather than specific delivery timelines.