SAP Certified Application Associate – SAP S/4HANA Sales (2022) — Question 14
In which type of outline agreement would you see details of confirmed material quantities and delivery dates?
Answer options
- A. General value contract
- B. Quantity contract
- C. Scheduling agreement
- D. Material-related value contract
Correct answer: C
Explanation
The correct answer is C, Scheduling agreement, as it specifically includes confirmed material quantities and delivery dates. The other options, like the General value contract and Material-related value contract, do not focus on confirmed quantities and dates, while a Quantity contract is more about the total quantity rather than specific delivery timelines.