SAP Certified Application Associate – SAP S/4HANA Asset Management (2021) — Question 21
The technical completion of the current maintenance order was posted with a delay of 5 days.
What happens to the next planned date if you set the shift factor for early completion to 100%?
Answer options
- A. It is postponed by a full cycle (100%).
- B. It is postponed by 5 days.
- C. It is not shifted.
- D. It will be 5 days earlier.
Correct answer: C
Explanation
The correct answer is C because setting the shift factor to 100% for early completion does not affect the planned date; it remains the same. Options A and B suggest a delay, while D implies an advancement, which contradicts the effect of the shift factor in this scenario.