SAP Certified Application Associate – SAP S/4HANA Asset Management (2021) — Question 21

The technical completion of the current maintenance order was posted with a delay of 5 days.
What happens to the next planned date if you set the shift factor for early completion to 100%?

Answer options

Correct answer: C

Explanation

The correct answer is C because setting the shift factor to 100% for early completion does not affect the planned date; it remains the same. Options A and B suggest a delay, while D implies an advancement, which contradicts the effect of the shift factor in this scenario.