SAP Certified Application Associate – SAP S/4HANA Asset Management (2021) — Question 20
Which statements regarding a maintenance order with status REL are correct? (Choose three.)
Answer options
- A. Goods receipts for external services can be entered.
- B. The planner can change planned costs at the operation level.
- C. Shop papers can be printed only after the order release.
- D. The controller can determine actual cost surcharges.
- E. The planner can change estimated costs only at the header level.
Correct answer: A, B, C
Explanation
Options A, B, and C are correct because they accurately describe functions available once a maintenance order is released. Option D is incorrect as it pertains to controller functions that are not specified for orders in REL status, while option E is wrong because the planner has the ability to change estimated costs beyond just the header level.