Salesforce Field Service Lightning Consultant (legacy) — Question 1

Universal Containers wants to measure their adherence to specific SLAs for all Work Orders.
In which order should a Consultant implement the setup to achieve this requirement?

Answer options

Correct answer: B

Explanation

Option B is correct because establishing the Entitlement Process for Work Orders is essential first to ensure that the SLAs are defined before setting up Milestones and creating Entitlement records. The other options misplace the sequence, which would lead to incomplete SLA tracking configuration.