Salesforce Certified Business Analyst — Question 26
The business analyst (BA) at Universal Containers (UC) wants to understand why UC failed to meet a deployment date for its product go live while following the Agile process. According to the BA's research, the developers lacked a sense of the work in progress and the intended goal of that work, and the QA team was unable to dearly test the functionality based on a given persona.
Which step should the BA take next?
Answer options
- A. Create a SWOT (strength, Weakness, Opportunity. Threat) analysis to understand why development and testing took more time.
- B. Move the deployment date out so the teams have more time to work.
- C. Review the user stories to ensure they are small, testable, and valuable.
Correct answer: C
Explanation
The correct answer is C because reviewing user stories ensures they are appropriately sized and clear, which is essential for effective Agile development and testing. Options A and B do not directly address the underlying issues with the user stories that contributed to the deployment delay.