PRINCE2 Practitioner — Question 44
PRINCIPLES -
During stage 2, Learn-it decided, at a strategic level, that it will no longer deliver training to public sector organizations. It will only deliver training to the private sector.
Which action is an appropriate application of the ‘continued business justification’ principle, and why?
Answer options
- A. Stop the project, because this allows the project’s budget to be reinvested in a more worthwhile project.
- B. Stop the project, because the project is no longer making a positive contribution to the organization.
- C. Review the business case, because the justification for the project should be recorded and approved.
- D. Review the business case, because the project must have business justification throughout the project lifecycle.
Correct answer: C
Explanation
The correct answer is C because it emphasizes the need to review and validate the business case for the project, ensuring that it remains justified in light of the strategic shift. Options A and B suggest stopping the project without considering the justification, while D, although relevant, does not specifically address the need for documentation and approval of the business case.