PRINCE2 Practitioner — Question 28

The Sales Director would like to add a new company logo to the 'marketing material'. The change to the project scope has been approved by the project board. It is expected to delay product and stage completion date by 3 days and cost £900. The stage 2 cost tolerance of +£1.000 has not been used. The change budget of £500 has not been used.
Which option describes how this change should be funded?

Answer options

Correct answer: B

Explanation

Option B is correct because the £900 needed for the logo change can be fully funded from the unused stage 2 cost tolerance, which is well above the required amount. Options A and D are incorrect as they involve unnecessary requests when there's sufficient budget available. Option C is wrong because it suggests requesting extra funding despite the available resources.