PRINCE2 Practitioner 6th Edition — Question 54
Which of the following reports does not contain any information on risk?
Answer options
- A. Issue Report
- B. Highlight report
- C. Lessons Report
- D. End Stage Report
Correct answer: A
Explanation
The Issue Report primarily focuses on documenting problems and issues that arise during a project, without addressing risk factors. In contrast, the Highlight Report, Lessons Report, and End Stage Report typically include discussions about risks encountered and how they were managed.