PRINCE2 Practitioner 6th Edition — Question 53
PRINCE2 proposes 3 levels of Plan, which are they?
Answer options
- A. Initiation, Project and Stage Plans
- B. Project, Stage and Exception Plans
- C. Initiation, Project and Benefit Review Plans
- D. Project, Stage and Team Plans
Correct answer: D
Explanation
The correct answer is D, as PRINCE2 outlines Project, Stage, and Team Plans as the three distinct levels of planning. Options A, B, and C include incorrect elements that do not align with the PRINCE2 framework for planning levels.