PRINCE2 Practitioner 6th Edition — Question 19

Which of the following is NOT a trigger for the project manager to authorize a work package?

Answer options

Correct answer: D

Explanation

The correct answer is D because reporting highlights are typically used for communication and do not constitute a formal trigger for authorizing work packages. In contrast, Stage Authorization, Corrective Action, and Exception plan approved are all direct triggers that require the project manager's approval to proceed with work packages.