PRINCE2 Practitioner 6th Edition — Question 19
Which of the following is NOT a trigger for the project manager to authorize a work package?
Answer options
- A. Stage Authorization
- B. Corrective Action
- C. Exception plan approved
- D. Reporting highlights
Correct answer: D
Explanation
The correct answer is D because reporting highlights are typically used for communication and do not constitute a formal trigger for authorizing work packages. In contrast, Stage Authorization, Corrective Action, and Exception plan approved are all direct triggers that require the project manager's approval to proceed with work packages.