The project is approaching the end of stage 3, and stage 4 is being planned as part of the 'managing a stage boundary' process.
Which action should the project manager carry out as part of the 'update the project plan' activity?

Answer options

Correct answer: A

Explanation

The correct answer is A because including the actual time and cost helps in tracking project performance and ensures that the project plan reflects current realities. Options B, C, and D do not directly pertain to updating the project plan with actual performance data, which is crucial at this stage.