PRINCE2 Foundation — Question 73
Which statement about the Directing a Project process is true?
Answer options
- A. Provides a mechanism for the Project Board to assure that there is continued business justification
- B. Covers the day-to-day activities of the Project Manager
- C. Ensures there are regular progress meetings
- D. Begins on completion of the Initiating a Project process
Correct answer: A
Explanation
The correct answer is A, as the Directing a Project process allows the Project Board to ensure that the project remains aligned with business objectives. Options B and C are incorrect because they pertain to the Project Manager's responsibilities and meeting schedules, which are not the main focus of this process. Option D is also wrong, as Directing a Project starts concurrently with the Initiating a Project process, not after its completion.