PRINCE2 Foundation — Question 73

Which statement about the Directing a Project process is true?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the Directing a Project process allows the Project Board to ensure that the project remains aligned with business objectives. Options B and C are incorrect because they pertain to the Project Manager's responsibilities and meeting schedules, which are not the main focus of this process. Option D is also wrong, as Directing a Project starts concurrently with the Initiating a Project process, not after its completion.