PRINCE2 Foundation — Question 72
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
Answer options
- A. Off-specifications
- B. Follow-on action recommendations
- C. Issue Register
- D. Risk Register
Correct answer: B
Explanation
The correct answer is B, as Follow-on action recommendations are specifically designed to identify tasks that need to be addressed after project closure. Options A, C, and D do not serve this purpose; Off-specifications refer to deviations from requirements, Issue Register tracks problems during the project, and Risk Register documents potential risks, not uncompleted work.