A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

Answer options

Correct answer: B

Explanation

The correct answer is B, as raising an off-specification is the appropriate action when a product does not meet the required standards. The other options, such as raising a request for change or amending the Work Package, do not directly address the immediate issue of the product's non-compliance.