If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
Answer options
- A. Checkpoint Report
- B. Highlight Report
- C. Issue Report
- D. Product Status Account
Correct answer: C
Explanation
The correct answer is C, the Issue Report, as it is designed to document and track issues, including changes requested during the project. The other options, such as the Checkpoint Report and Highlight Report, serve different purposes like progress reporting rather than detailing change requests.