PRINCE2 Foundation — Question 50

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

Answer options

Correct answer: B

Explanation

The correct answer is B, as those who manage the project on a daily basis are typically considered part of the project management team rather than primary stakeholders. Options A, C, and D all represent key categories of stakeholders in PRINCE2, including financial stakeholders, those defining project outputs, and those creating the outputs.