PRINCE2 Foundation — Question 50
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
Answer options
- A. Those with a financial interest in the project
- B. Those who will manage the project on a day-to-day basis
- C. Those who will specify the desired outputs of the project
- D. Those who will create the project's outputs
Correct answer: B
Explanation
The correct answer is B, as those who manage the project on a daily basis are typically considered part of the project management team rather than primary stakeholders. Options A, C, and D all represent key categories of stakeholders in PRINCE2, including financial stakeholders, those defining project outputs, and those creating the outputs.