PRINCE2 Foundation — Question 49
Which is an objective of the 'directing a project' process?
Answer options
- A. To tailor the project's products and roles so that the project suits the circumstances
- B. To respond to the project mandate by starting up a project
- C. To provide an interface between the project and corporate management
- D. To ensure the stage products are delivered to the stated quality standards
Correct answer: C
Explanation
The correct answer, C, highlights the importance of facilitating communication and alignment between project activities and corporate management. Options A, B, and D, while relevant to project management, do not specifically reflect the primary focus of directing a project, which is to ensure effective governance and oversight.