PRINCE2 Foundation — Question 47
According to PRINCE2, why might there be more than one business case for a project?
Answer options
- A. There may be more than one management stage in the project
- B. The project may be in a commercial environment with a number of suppliers
- C. There may be more than one work package being delivered in the project
- D. The project may be in a programme environment
Correct answer: B
Explanation
The correct answer is B because having multiple suppliers in a commercial environment can lead to the need for separate business cases to address each supplier's contributions and impacts. The other options focus on project structure or management aspects rather than the external commercial factors that necessitate multiple business cases.