PRINCE2 Foundation — Question 46
To meet the minimum requirements for applying the progress theme, what must be considered?
Answer options
- A. How lessons will be learned
- B. How time-driven reports will be produced
- C. Which management products will be baselined
- D. Who is responsible for reporting on progress
Correct answer: A
Explanation
The correct answer is A, as understanding how lessons will be learned is crucial for continuous improvement and adapting processes. The other options, while relevant to project management, do not directly address the foundational requirements of the progress theme.