PRINCE2 Foundation — Question 44

From whom does a Team Manager obtain approval for a completed product?

Answer options

Correct answer: C

Explanation

The correct answer is C because the authority responsible for approving a completed product is specified in the Product Description. Options A, B, and D do not hold the defined authority as per the project framework, thus they cannot provide the necessary approval.