PRINCE2 Foundation — Question 43

Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

Answer options

Correct answer: B

Explanation

Statement 2 is accurate because the Closing a Project process does include a review to determine if the objectives from the Project Initiation Documentation were met. Statement 1 is misleading as the process does not specifically denote a fixed point for Work Package receipt, making it false.