PRINCE2 Foundation — Question 346
Which is a purpose of the Initiating a Project process?
Answer options
- A. Decide if it is worthwhile to initiate a project
- B. Decide on the project approach
- C. Establish solid foundations for a project
- D. Identify the number of Work Packages required
Correct answer: C
Explanation
The correct answer is C, as the Initiating a Project process is designed to lay down a solid foundation for the project, ensuring that all necessary elements are in place before proceeding. Options A and B, while related to project management, do not specifically address the foundational aspect, and D focuses on a specific detail rather than the overall purpose of the process.