PRINCE2 Foundation — Question 345
In what process is the authorization to deliver the project's products given?
Answer options
- A. Starting up a Project
- B. Initiating a Project
- C. Managing a Stage Boundary
- D. Directing a Project
Correct answer: D
Explanation
The correct answer is D, as 'Directing a Project' involves making decisions regarding the delivery of project products. Options A and B refer to the initial phases of project setup, while C focuses on overseeing transitions between project stages, not granting delivery authorization.