PRINCE2 Foundation — Question 33
What must be done for a project to be a PRINCE2 project?
Answer options
- A. The project must form part of a programme or portfolio
- B. The project must meet the minimum requirements for applying the themes
- C. The project must use the recommended approach to planning
- D. The project roles must be combined wherever possible
Correct answer: B
Explanation
The correct answer, B, is essential because PRINCE2 projects need to adhere to specific themes that guide their execution. Options A, C, and D do not represent fundamental requirements for a project to be considered PRINCE2 compliant, as they pertain to broader organizational structures or methodologies rather than the core themes themselves.