PRINCE2 Foundation — Question 32
Which statement about project roles is CORRECT?
Answer options
- A. The project organization must be defined using the roles and responsibilities in PRINCE2
- B. The project team structure defined in PRINCE2 must be used, but other roles may be added
- C. The project board roles defined in PRINCE2 must be used, but other roles can be defined as required
- D. Any role can be defined as required the responsibilities defined in PRINCE2 are fulfilled
Correct answer: C
Explanation
The correct answer is C because it acknowledges that while the project board roles defined in PRINCE2 are essential, there is flexibility to define other roles as needed. Options A and B incorrectly suggest that the project organization and team structure must strictly adhere to PRINCE2 without room for additional roles. Option D misrepresents the importance of adhering to PRINCE2 responsibilities while allowing for role flexibility.