PRINCE2 Foundation — Question 322
How should the Team Manager report that tolerances are forecast to be exceeded?
Answer options
- A. Create an Exception Report
- B. Create a Highlight Report
- C. Raise an issue
- D. Grant a concession
Correct answer: C
Explanation
The correct answer is C, as raising an issue is the proper procedure to address the potential exceeding of tolerances. An Exception Report is used for formal reporting after an issue has been raised, a Highlight Report summarizes project status, and granting a concession does not directly address the forecasted tolerance breach.