PRINCE2 Foundation — Question 321

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

Answer options

Correct answer: C

Explanation

The correct answer is C, as a Work Package is a defined portion of work within a project, and its cost tolerance is specifically agreed upon between the Project Manager and Team Manager. The other options refer to broader or different scopes within project management and do not fit the specific context of agreeing on a Work Package.