PRINCE2 Foundation — Question 314

Identify the missing words in the following sentence.
Project assurance personnel [ ? ] the project manager.

Answer options

Correct answer: D

Explanation

The correct answer is D because project assurance personnel are responsible for reporting to the project board, which includes the project manager in the oversight process. Options A and B misrepresent the role of project assurance personnel, as they do not have authority over decisions nor are they directly accountable to the project manager. Option C, while implying support, does not accurately capture the primary accountability to the project board.