PRINCE2 Foundation — Question 295
Identify the missing word(s) in the following sentence:
[ ? ] dependency is one between two products of a project, over which the project team has control.
Answer options
- A. An internal
- B. A schedule-driven
- C. An external
- D. A resource-driven
Correct answer: A
Explanation
The correct answer is 'An internal' because it refers to dependencies that the project team can manage directly. The other options, such as 'A schedule-driven,' 'An external,' and 'A resource-driven,' do not imply control by the project team as they involve factors beyond direct influence.