PRINCE2 Foundation — Question 294
The senior user needs to understand how user assurance will support the senior user on the project.
Which management product should the senior user review?
Answer options
- A. Project plan
- B. Project management team structure
- C. Role descriptions
- D. Project log
Correct answer: C
Explanation
The correct answer is C, as role descriptions provide detailed information on responsibilities and user assurance's role in supporting the senior user. Options A and B focus on the overall project structure rather than specific user support, while D pertains to project records, which do not directly address user assurance.