PRINCE2 Foundation — Question 292

According to the ‘exception management’ technique, which roles are MOST LIKELY to identify issues that exceed stage tolerances?

Answer options

Correct answer: D

Explanation

The correct answer is D, as the Project Manager and Team Manager are directly involved in the day-to-day operations and are responsible for monitoring project performance against tolerances. The other options include roles that may not have the same level of oversight or direct involvement in identifying issues that exceed established tolerances.