PRINCE2 Foundation — Question 291
The project manager is acting as the team manager and needs to control the work of a team member who reports to them.
Which management product should the project manager use to control this work?
Answer options
- A. A work package description
- B. The project management team structure
- C. A stage plan
- D. A work breakdown structure
Correct answer: A
Explanation
The correct answer is A, as a work package description provides detailed information about the tasks to be completed, allowing the project manager to effectively oversee the team member's work. The other options, while important for overall project management, do not provide the specific control needed for individual tasks.