PRINCE2 Foundation — Question 288
The project manager needs to monitor the progress of the stage.
Which combination of management products should the project manager review?
Answer options
- A. Checkpoint reports AND work package descriptions
- B. Project plan AND project log
- C. Project plan AND work package descriptions
- D. Highlight report AND checkpoint report
Correct answer: D
Explanation
The correct answer is D because the Highlight report provides an overview of the stage's progress, while the Checkpoint report offers detailed insights into current status and issues. The other options do not provide the same combination of comprehensive progress tracking needed for effective monitoring.