PRINCE2 Foundation — Question 287

According to the ‘manage by exception’ principle, which statement about tolerances is CORRECT?

Answer options

Correct answer: B

Explanation

The correct answer is B because the 'manage by exception' principle necessitates that any potential breaches of tolerance are escalated to the project board for their attention. Options A and D are incorrect as they misinterpret the delegation of authority and focus, while option C inaccurately suggests a delay in addressing tolerance issues until the next meeting.