PRINCE2 Foundation — Question 287
According to the ‘manage by exception’ principle, which statement about tolerances is CORRECT?
Answer options
- A. Whenever authority is delegated to the project manager, the project board should set tolerances for the stage
- B. Whenever there is a forecast to exceed a tolerance, it should be escalated to the project board
- C. Whenever there is a forecast to exceed a tolerance, it should be resolved at the next monthly project board meeting
- D. Whenever authority is delegated to the team manager, the focus should be on delivering within time and cost tolerances
Correct answer: B
Explanation
The correct answer is B because the 'manage by exception' principle necessitates that any potential breaches of tolerance are escalated to the project board for their attention. Options A and D are incorrect as they misinterpret the delegation of authority and focus, while option C inaccurately suggests a delay in addressing tolerance issues until the next meeting.