PRINCE2 Foundation — Question 285
Which describes a management activity within a project?
Answer options
- A. Encouraging a project team to continue working on a particularly challenging product
- B. Discussing protect objectives with key stakeholders during a requirements gathering workshop
- C. Agreeing a work package with a team manager to deliver products within agreed Tolerances
- D. Seeking feedback from team members to ensure they are still aligned to the project's objectives
Correct answer: C
Explanation
The correct answer, C, highlights the formal agreement of a work package, which is a key management function ensuring deliverables meet project tolerances. Options A, B, and D involve supportive or communicative actions but do not represent the same level of management responsibility as agreeing on work packages.