PRINCE2 Foundation — Question 284
As part of the ‘closing a project’ process, the project manager needs to assess whether the outcomes are likely to deliver the expected performance improvements post-project.
In which step of 'business case management' technique should the project manager assess this?
Answer options
- A. Develop
- B. Check
- C. Maintain
- D. Confirm
Correct answer: D
Explanation
The correct answer is D, Confirm, because this step is specifically focused on validating that the project outcomes align with the expected benefits. The other options, while relevant to different phases of business case management, do not specifically address the assessment of performance improvements post-project.