PRINCE2 Foundation — Question 234
The project manager reviews the project product description to identify the detailed requirements for each product.
In which step of the quality management technique should the project manager do this review?
Answer options
- A. Gathering user inputs
- B. Accepting products
- C. Describing the quality management approach
- D. Controlling quality
Correct answer: C
Explanation
The correct answer is C, as this step involves establishing a clear understanding of quality requirements based on the product description. Options A and B are focused on gathering input and accepting deliverables, while D pertains to monitoring quality, rather than defining it.