PRINCE2 Foundation — Question 234

The project manager reviews the project product description to identify the detailed requirements for each product.

In which step of the quality management technique should the project manager do this review?

Answer options

Correct answer: C

Explanation

The correct answer is C, as this step involves establishing a clear understanding of quality requirements based on the product description. Options A and B are focused on gathering input and accepting deliverables, while D pertains to monitoring quality, rather than defining it.