PRINCE2 Foundation — Question 233

When does the ‘directing a project’ process start?

Answer options

Correct answer: D

Explanation

The 'directing a project' process begins only after the project mandate has been received, as this document provides the necessary authority and direction for the project. The other options involve preliminary steps that do not grant the authority needed to initiate the directing process.