PRINCE2 Foundation — Question 203
Which describes a risk effect?
Answer options
- A. The uncertainty expressed as a negative or favourable occurrence
- B. The issue which is affecting the project and has resulted in a risk
- C. The impact(s) on the project objectives should the threat or opportunity occur
- D. The change in the status of a risk in response to actions taken to control it
Correct answer: C
Explanation
The correct answer, C, accurately describes the potential impacts on project objectives should a risk materialize. Option A refers to the uncertainty of risks rather than their effects, B discusses issues rather than consequences, and D focuses on changes in risk status instead of the effects on objectives.