PRINCE2 Foundation — Question 202
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
Answer options
- A. Risk category
- B. Risk description
- C. Risk response
- D. Risk status
Correct answer: C
Explanation
The correct answer is C, Risk response, as it specifically refers to the strategies implemented to manage and mitigate risks. Options A, B, and D do not pertain to the actions taken to address risks but rather describe classifications, explanations, or current conditions of risks.