PRINCE2 Foundation — Question 188
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
Answer options
- A. Directing a Project
- B. Controlling a Stage
- C. Managing a Stage Boundary
- D. Managing Product Delivery
Correct answer: B
Explanation
The correct answer is B, Controlling a Stage, as it focuses specifically on monitoring and controlling the progress of a stage to ensure it remains within defined tolerances. The other options, while related to project management, do not specifically address the ongoing oversight and control necessary during a stage's execution.