PRINCE2 Foundation — Question 187
In which process are corrective actions taken to ensure that the management stage remains within tolerance?
Answer options
- A. Directing a project
- B. Managing product delivery
- C. Controlling a stage
- D. Managing a stage boundary
Correct answer: C
Explanation
The correct answer is C, as 'Controlling a stage' specifically involves monitoring the stage's progress and implementing corrective actions if required to ensure it stays within set tolerances. The other options do not focus on the corrective actions necessary for maintaining stage management but rather on broader project or boundary management aspects.