PRINCE2 Foundation — Question 154
Which should be funded by a change budget?
Answer options
- A. Increase in agreed scope
- B. Initiation stage
- C. Change Authority
- D. Handover activities
Correct answer: A
Explanation
The correct answer, A, refers to an increase in agreed scope which typically requires additional funding to accommodate the changes. Options B, C, and D do not usually necessitate extra funds from a change budget, as they pertain to foundational project phases or governance rather than adjustments in scope.