PRINCE2 Foundation — Question 153
Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.
Answer options
- A. Management strategies
- B. Plan
- C. Stakeholder interests
- D. Time-driven controls
Correct answer: B
Explanation
The correct answer is 'Plan' as PRINCE2 emphasizes the importance of planning at different levels to meet management needs. The other options, while relevant to project management, do not specifically address the structured approach to planning that PRINCE2 advocates.